The screed should be poured so that no voids remain.
Posted: Sun Feb 09, 2025 10:29 am
EPS is covered with a vapor barrier film with an overlap, the joints are glued. The film is placed on the walls and connected to the vapor barrier of the walls to prevent rotting of the load-bearing beams of the structure.
In case of building a furnace in the future, the place left without EPS is reinforced with a metal grid, enclosed with formwork, and a screed is poured. - Next comes the laying of a metal grid over the entire area and installation of contours and elements of a heated floor - electric or water (if this is in the project);
A finishing screed made of a mixture of cement and sand is poured along the beacons. Otherwise, cracks may appear, which will lead to the failure of the elements of the heated floor.
Complete drying of the screed takes 14-28 days. It should dry naturally, without using heating systems and without turning on the heated floor. Only after this can you start laying the finishing coating, which can be wooden (removable) or tiled.
In the second case, the screed is covered with a primer and faced with ceramic tiles using tile adhesive.
Concrete floor
It is rarely used, but in practice it is sometimes encountered. But it should be cameroon mobile database acceptable only for solid soil, where piles are chosen as a foundation for technical reasons.
Information! A concrete floor is bulky, difficult to install and requires significant financial costs. However, unlike wooden floors, it is not subject to deformation and is designed for a long service life.
A distinctive feature of this design is the use of welded I-beams as joists.
First, you need to prepare the foundation of the bathhouse floor. For this, the support piles are calculated and screwed along the perimeter of the structure - along the load-bearing walls with a certain step - individual for the dimensions of a particular building.
I-beams are attached to piles covered with a layer of waterproofing. Such beams are especially strong due to the design with a stiffening rib. They are able to withstand and not bend even under a large weight (for example, when erecting a two-story building on such a foundation).
The next element of the structure is corrugated sheeting, which is screwed to the beams due to the presence of factory perforation in them. The corrugated sheeting should be selected with a thickness of at least 1.2 mm. with a wave crest height of at least 15 mm. The corrugated sheeting waves are filled with a rough screed. Extruded polypropylene or dense foam plastic slabs are laid on the screed dried in natural conditions.
In case of building a furnace in the future, the place left without EPS is reinforced with a metal grid, enclosed with formwork, and a screed is poured. - Next comes the laying of a metal grid over the entire area and installation of contours and elements of a heated floor - electric or water (if this is in the project);
A finishing screed made of a mixture of cement and sand is poured along the beacons. Otherwise, cracks may appear, which will lead to the failure of the elements of the heated floor.
Complete drying of the screed takes 14-28 days. It should dry naturally, without using heating systems and without turning on the heated floor. Only after this can you start laying the finishing coating, which can be wooden (removable) or tiled.
In the second case, the screed is covered with a primer and faced with ceramic tiles using tile adhesive.
Concrete floor
It is rarely used, but in practice it is sometimes encountered. But it should be cameroon mobile database acceptable only for solid soil, where piles are chosen as a foundation for technical reasons.
Information! A concrete floor is bulky, difficult to install and requires significant financial costs. However, unlike wooden floors, it is not subject to deformation and is designed for a long service life.
A distinctive feature of this design is the use of welded I-beams as joists.
First, you need to prepare the foundation of the bathhouse floor. For this, the support piles are calculated and screwed along the perimeter of the structure - along the load-bearing walls with a certain step - individual for the dimensions of a particular building.
I-beams are attached to piles covered with a layer of waterproofing. Such beams are especially strong due to the design with a stiffening rib. They are able to withstand and not bend even under a large weight (for example, when erecting a two-story building on such a foundation).
The next element of the structure is corrugated sheeting, which is screwed to the beams due to the presence of factory perforation in them. The corrugated sheeting should be selected with a thickness of at least 1.2 mm. with a wave crest height of at least 15 mm. The corrugated sheeting waves are filled with a rough screed. Extruded polypropylene or dense foam plastic slabs are laid on the screed dried in natural conditions.